Tuesday, August 4, 2009







The Internet is finally working! Everyone got to Haiti in fine shape and we have been hard at work on the project. We have had a little problem getting all of our luggage as usual, but today all but one of them finally came. The plywood and steel are about 75% complete and then they must form the edges of the roof before they pour. The plumbing and electical are nearly complete on the roof so the pouring can start soon.
We are not sure when the groups will come to start the roof, but some of the workers are saying Thursday. We aren't sure that will happen.

There is a big difference in heat between March when we usually come and this trip in August. All in all though it hasn't been too bad with a nice breeze when you are on the roof.

Hopefully the Internet will stay up so be sure to check back daily. See you all later.